Posted inArmidale, Energy, Feature, Walcha

Walcha “gobsmacked” as Armidale votes to object to REZ transmission EIS

New England REZ EIS cover (screenshot)

Armidale Regional Council has voted unanimously to object to the New England Renewable Energy Zone (REZ) transmission project as it stands, while Walcha Council says it was left “gobsmacked” by errors in the project’s environmental impact statement (EIS).

Submissions on the EIS close at midnight tonight, Thursday, 26 November.

Armidale councillors endorsed a 141-page submission at their meeting on Wednesday, 25 November. It objects to approval of the project “as currently proposed and assessed”.

“The EIS, as presented, addresses major structural challenges such as water security by effectively giving council and, by extension, the wider community an IOU, where they’ve identified the problem, minimised it, and then said a solution will be forthcoming. Trust us,” said Mayor Sam Coupland.

The project, run by EnergyCo, would include a 330 kV switching station at Boorolong, off Romani Road, known as the North Hub. Construction would start in 2028 and take six or seven years.

Water was the sticking point for councillors. The project needs about 2,400 megalitres for construction, including 360 megalitres of drinking water, and Armidale’s submission says none of it is secured.

“We’re a community that’s already faced the prospect of evacuation due to drought only six years ago, and this project doesn’t appear to recognise this at all,” said Cr Todd Redwood.

“I’m not suggesting that we’re opposed to the REZ, but that said, it doesn’t provide unqualified support for it.”

“You can’t make it rain just because you want it to rain, and that’s effectively what we heard when we spoke to the people that presented the EIS.”

Cr Kay Endres said EnergyCo could not answer where the water would come from if there was none.

“We’ve all just lived through a drought not very long ago, and realised that when there’s no water anywhere, there is no water,” she said.

Armidale Regional Landfill is operating at its licensed annual limit, and the submission says more than 50 kilometres of council roads designed for light traffic would carry part of about four million tonnes of construction materials.

“The waste is astonishing, and we need to do something about it,” said Cr Susan McMichael.

Cr Bradley Widders took aim at the EIS leaving key decisions to a network operator yet to be appointed.

“It just sounds like something I would have come up with in year four to try and get my mum and dad to buy me something,” Cr Widders said.

Walcha “decidedly disappointed”

Walcha Council’s draft submission, signed by General Manager Stephen Parry, went to its meeting on Wednesday afternoon with a recommendation that council endorse it.

“Walcha Council is decidedly disappointed and deeply uncomfortable with the New England REZ Transmission Project Environmental Impact Statement,” the submission states.

“Walcha Council is disappointed to the point of being gobsmacked by the numerous inconsistencies and inadequacies in this EIS.”

The submission says the EIS overstates Walcha’s population by nearly double, and that the village of Walcha Road, with a population of 70, “would be next door to a workers camp of up to 550 workers”.

“To add insult to injury, Walcha’s First Nations people have not been genuinely consulted with no recorded meetings held in Walcha,” the submission states.

It also points out the spelling of Dunghutti used by the Amaroo Local Aboriginal Land Council does not appear in the EIS.

On traffic, Walcha says the EIS did not model the busiest period at Camp 4, when the workforce there is expected to more than double to 500 over the summer of 2031โ€“32. The submission also raises concerns about two bridges on Thunderbolts Way, over Ohio and Bergen Op Zoom creeks.

“Council is extremely concerned that each project will find no upgrades are required for Thunderbolts Way and, despite its inclusion in the Port-to-REZ maps, Council will be left with a huge maintenance bill,” the submission states.

Walcha also says the EIS assumes water for Camp 4 will come from the Apsley-Macleay water sharing plan, when it is much more likely to come from the Macdonald-Namoi.

EnergyCo approved up to $95,000 for consultants to help Walcha review the EIS. Avandra Advisory reviewed the traffic assessment and LAMAC Consulting reviewed the whole document.

Walcha’s council survey drew 173 responses, mostly from ratepayers, and 11 residents addressed council on issues including farming, aviation, biosecurity, cost of living, and noise, light, and traffic from Camp 4.

Both councils say they are not opposing the REZ itself, and Armidale has left the door open to change its position if the gaps are filled.

“If the gaps that underlie its objection were addressed and the information in this submission were publicly considered against the project, Council may review its decision,” Armidale’s submission states.

Walcha’s submission ends on a sharper note.

“Given the time EnergyCo afforded itself in having the EIS in gestation, the birthing of this document before an expectant public has proven to be a disenchanting experience,” it states.


Got something you want to say about this story? Have your say on our opinion and comment hub, New England Times Engage

RK Crosby is a broadcaster, journalist and pollster, and publisher of the New England Times.